Client
Deloite and Touche
Design Brief
To carry out a
visual survey only of the Landlord's mechanical and electrical
component parts in order to assess their life expectancy
and likely replacement costs.
Plant information was verified by reference to the site
maintenance logs.
The site survey conducted sought to provide
a visual inspection of the principal component parts, with
internal inspections of plant where deemed acceptable,
and not affecting the continued operation of the system.
Principle plant items contained
within the report
- Boilers
- Burners
- Pressurisation Unit
- DHW Storage Calorifiers
- HWS Secondary Pumps
- LTHW Heating Pumps
- CHW Pumps
- Condensate Pumps
- Radiators
- Main Landlord's Switchboard
- Distribution
Boards
- Mechanical Controls Panels
- Staircase Lighting
- Fire Alarm System
- GRP Sectional Tank
- Chillers
- Chilled Water System Primary Pumps
- HVAC Office
Supply & Extract Plant
- Cooling Tower
- Toilet Blocks
- Hosereels